Highland Community Center Play Area (updated 6/29/18)

2018

This project is on schedule for 2018.  Construction of the Highland Community Center Play Area is on track for completion by the end of this summer.  Here’s a timeline:

  •  March 19 – Advertise project for bids
  • April 11 – Bids due
  • Mid April – Recommend award for contract
  • Mid May – Contract awarded
  • Late May, June, July – Construction
  • Late July/Early August – Completion

Approved Site Plan (6/29/18)
Final_ SPR Approval – HPCC Play Area – 06262018
180111 Highland Play Area SPR plan package
Highland Community Center Play Area Survey
SPR application with notes

2017

An OPEN HOUSE has been scheduled for Monday October 16th from 5:00 – 7:00 in the Highland Community Center Community Room.  Proposed play area layout, play equipment, and site amenity plans will be presented for review and feedback from the community.

Highland Playground Open House Flyer

Overview:  Replace play equipment and make additional improvements including walkways, benches, landscaping and/or signage as funding allows.

For more information and updates to to:

HPCC Play Area